- The final product! Very exciting to have it done!!!
- The crew worked so quickly and so well together – each of them had different jobs and it was really neat to watch how orchestrated the pour was. You can tell they had all been working together for a while and really knew what they were doing. They were making it look easy – but it was definitely hard work.
- Here’s the pump truck – you can really see how uneven and sloped our future driveway is right now!
- The arm on the pump truck was so big!
- The concrete and pump trucks were situated up by the road with the arm of the pump truck reaching over the basement wall.
- Here’s Cameron, standing in the garage with it backfilled part of the way – he’ll never get to do that again!
- Most of the backfilling around the basement had been done by now, and it’s pretty awesome to see the backyard grading start to take shape.
- Here’s what the house looked like at the start of the week.
- All of the plumbing that had to be run in the basement slab was installed.
- Here’s Spencer standing next to the house – he was all about getting filthy dirty today. At one point he even kicked his sandals off. Ick – those went back on – immediately!
- In action – regrading the back patio area…and the plumber looking annoyed about the digging!
- By the end of the week, here’s what the progress looked like in panorama.
- The first layer of the waterproofing, a bituminous spray-on, has been applied.
- Here they are adding more gravel for the base material (and for drainage underneath the basement slab).
- This is the 2nd layer of the waterproofing, a dimpled membrane with geotextile – American Wick Sheetdrain 180
- By the end of the day on Friday it’s all formed and ready for the pour on Monday!
- At work it’s standard to have “safety moments” before each meeting…had to share this one.
- Here’s the garage – it seems like such a waste that it’s all going to be filled in with dirt – we’re not having any living space beneath the garage. Cameron wanted to make it an indoor basketball court! There’s an idea!
- A quick pic inside the walls at Spencer’s room.
- Rebar at sunset – whata view!
- Cameron always wants to check the progress out with me! Love it!
- Here’s the concrete pump truck.
- I wish the boys were here to see this – this guy has a remote control to maneuver the articulating robotic arm of the pump truck.
- These guys have the scary work – standing on top of 10′ walls, filling them with concrete and then vibrating them. My dream job? No thank you!
- The formwork has all been stripped and now you can really see the concrete walls & footings in the basement.
- Another view of the basement walls – this time from standing in the (future) back yard.
- By Friday they started to fill the footings with gravel using a conveyor belt system. Reminds me of working on I-405!
- Here’s the finished product Wednesday night…we have footings!
- Check out that rebar 🙂
- There’s Cameron on Thursday – standing in his bedroom.
- The guys even worked the Friday before the 4th of July! Lucky for us! And they started to form the walls up in the basement.
- On Wednesday they poured the footings. From the concrete truck to the pump to our footings.
- They reached over the excavated area to get to our footings.
- Another picture of the pump and our footings.
- By the end of the day on Tuesday the formwork was up and pretty close to being ready for concrete.
- Here’s a shot of Joel and the boys standing next to the excavation for the basement – just to give you some scale.
- Just some quick math for the garage retaining wall’s footing…they must have run out of graph paper 😉
- Monday they made all the cuts and had it laid out.





































