Week 9: Lower Level Framing has Begun

This week marked a huge milestone with the completion of the foundation and basement slab and the beginning of framing.  Big deliveries of the lumber for our house too!  We opted to use Douglas Fir which is regarded as the highest standard for framing material – all other woods are measured against Douglas Fir because of its high strength, stability values, and excellent performance against strong wind forces.  Did you know Douglas Fir isn’t actually a true fir tree?  It’s scientific name “Pseudotsuga” actually means “false hemlock”…how strange is that?

Anyhow, the builder’s standard would have been to use a Hem-Fir which is a combination of lumber from western hemlocks and true firs (nobles, grand, pacific silver, etc).  Hem-Fir has a lower strength value than Douglas Fir, but it’s still capable of meeting the engineer’s span requirements.  So Hem-Fir would have suited our building needs, but my dad insisted that we upgrade to Douglas Fir.  Dad knows best, huh?!  He thinks we’ll end up with straighter and stronger walls.  Stronger walls…maybe. That was the case with ‘old growth’ Douglas Fir – which isn’t really around anymore.  Everything now is fairly ‘young’ and our builder thinks that now there’s not much of a difference in strength between Hem-Fir and Douglas-Fir lumber.  In any case, we opted for the upgrade to the stronger Douglas Fir.

Lumber was delivered to the property this weekend.

Lumber was delivered to the property this weekend.

Each piece of lumber has a stamp on it which describes the wood species, grading, and processing.  Here's an example of ours.

Each piece of lumber has a stamp on it which describes the wood species, grading, and processing. Here’s one of ours.

Also delivered was a lot of the material needed for the floor system between the two floors.  This includes our plywood, TJI joists, and some laminated strand lumber needed in certain spots.  Our engineer spec’d for us to use 110 TJI’s at 24″ on center spacing with 3/8″ plywood sheeting for the subfloor, but we opted to use 210 & 560 TJI’s at 16″ on center spacing with 1 1/8″ plywood sheeting.  So we’re using stronger TJI joists, at a closer spacing, and with thicker plywood – this results in a much stronger floor system, without any deflection or ‘bounciness’ in the floor.

A lot of the lumber for the house was delivered this week!

Even some of the material for the flooring system between the main and lower levels were delivered, including our 1 1/8″ tongue & groove plywood subfloor, Laminated Strand Lumber (LSL’s) and our TJI joists.

Ok, to the fun stuff…the guys started framing the house last Saturday, by snapping lines and prepping for the sill plates.  It’s amazing to see the amount of work they can get done in just one week.  The majority of the basement walls have been framed and you can walk through each of the rooms now.  After working on designing the house for a year, it’s crazy to see it actually taking shape and being able to walk through all of the rooms.  Now that we can walk through them, all of the rooms’ dimensions feel really good – I don’t think any of the rooms feel too small (which I was a little worried about in the guest room).  And the only space that feels big is the storage room downstairs – I guess that’s expected though since it’s 620 square feet!  It’s going to be so nice to actually have some storage in a house – we were definitely missing that in our old house and our garage was always filled with ‘junk’ (as Joel says), like Christmas decorations, patio furniture, and camping gear.  And now that we added a door to the backyard into the storage room we’re really going to be able to access it easily.  Super excited for that space!

Check out our lower level!  It's so awesome to see it go up and be able to walk through it now!  Absolutely surreal!

Check out our lower level! It’s so fantastic to see it go up and be able to walk through it now!

It's so awesome to walk down the property and see the house!  This is looking south at the house, which is Spencer's room on the corner.

It’s so awesome to walk down the property and see the house! This is looking south at the house, which has Spencer’s room on the closest corner.

Here's 4 out of 5 of the windows in the guest room.

Here’s 4 out of 5 of the windows in the guest room.

This is a good look at what it'll feel like in the downstairs rec room.  All said and done, there will be two double doors with a pair of windows in between them.

This is a good look at what it’ll feel like looking out of the downstairs rec room. All said and done, there will be two double doors with a pair of windows in between them.

Here's the framing so far in the boys' playroom.

Here’s the framing so far in the boys’ playroom.  There will be a couch to the right and a TV & art center on the left wall.  The boys’ bathroom is straight ahead and bedrooms are in the far right corner.

Here's what the house looks like from the road as you drive up - so much progress this week!

Here’s what the house looks like from our street as you drive up.  They’ve already got the trusses laying down, which they’ll be installing the first part of next week.  It’ll be crazy to see the main level being worked on next week for sure!  Then it’ll actually look like a house from the street!

Here's a view of what those trusses look like from down below...I'm sure they'll be standing them up on Monday.

Here’s a view of what those trusses look like from down below…I’m sure they’ll be standing them up on Monday.

Week 8: Basement Slab & Passed our Well Report

This week flew by fast, and it was awesome to see the progress on the house.  At the beginning of the week they were busy working on backfilling and grading around the house, and installing the plumbing lines that needed to be in the basement slab.  I was there on Tuesday morning to talk with Matt about some of the site grading and already they were testing the plumbing to ensure there wasn’t any leaks in the pipe network.  To do this they ran a garden hose from our well up to the house – how crazy is it that we’re already using the water!?!

Here's what the house looked like at the start of the week.

Here’s a panoramic of what the house looked like at the start of the week.

Most of the backfilling around the basement had been done by now, and it's pretty awesome to see the backyard grading start to take shape.

Most of the backfilling around the basement had been done by now, and it’s pretty awesome to see the backyard grading start to take shape.

Here's Cameron, standing in the garage with it backfilled part of the way - he'll never get to do that again!

Here’s Cameron, standing in the garage with it backfilled part of the way – he’ll never get to do that again!

A good amount of site grading occurred this week.  A bit more heavy equipment was on site.

A good amount of site grading occurred this week. A bit more heavy equipment was on site.

All of the plumbing that had to be run in the basement slab was installed.

All of the plumbing that had to be run in the basement slab was installed.

Speaking of that, Matt brought a sample of the well water to AMTest Laboratories for bacterial testing.  With a $10 upgrade for overnight results, on Tuesday we received the word that our water passed – no amounts of bacteria were present!  Such a relief, because that test result coupled with our well log meant that we had our source of water and the bank would be able to now allow us to draw on our construction loan.  Phew!  I also dropped off some more water to test for a complete scan which will include testing for nitrates, arsenic, ph levels, etc.  Those results will be back in two weeks.

Check out Cameron with the water coming out of the well...like a fire hose!

Check out Cameron with the water coming out of the well like a fire hose!

Our well log - finally!  This well log + bacterial test results on the water = construction funding!

Our well log – finally! This well log + bacterial test results on the water = construction funding!

Every day there seemed to be a bit of progress, but it felt like it really moved along towards the end of the week.  On Wednesday and Thursday they were leveling out the gravel in the slab, installing the vapor barrier and the rigid foam insulation over the entire slab.

Here you can see the vapor barrier (black plastic) and a bit of the rigid foam insulation which is installed underneath the concrete slab.  To meet King County's energy codes, we opted to install R-10 insulation underneath our entire slab.  That'll also help keep the boys' toes toasty in the winter.

Here you can see some of the vapor barrier (black plastic) and a bit of the rigid foam insulation which is installed underneath the concrete slab. To meet King County’s energy codes, we opted to install R-10 insulation underneath our entire slab. That’ll also help keep the boys’ toes toasty in the winter.

R-10 rigid foam insulation all stacked up before it was installed

R-10 rigid foam insulation all stacked up before it was installed

Friday was when all of the fun happened though.  Our oldest, Cameron, had a soccer tournament all day, so I took the day off of work to be the ‘soccer mom’ and drive him up to Burlington.  But we didn’t have to leave for the first game until 10:30am, so we went out to check out the construction going on – and it was so much fun.  They were pouring basement slab on Friday so we really got to see a lot of great construction going on.  My dad even met us out there (actually got there before we did) and we all hung out for a couple hours.  Cameron had a blast and a ton of questions too!

We talked to the slab guy (Jeremy) a bit and he said that because it’s been so hot (95 degrees) out, he added in a retarder to slow down the concrete curing.  If concrete cures too fast, it will crack, and even though they started pouring at 8am, it takes at least a full 24 hours for the main curing to occur, so the afternoon heat could have really done some damage.  To help it stay cool even longer, in the early afternoon they sprayed water all over the slab to saturate and cool it down.  Without slowing down the curing, the concrete will dry (and crack) before gaining it’s full tensile strength.

The concrete and pump trucks were situated up by the road with the arm of the pump truck reaching over the basement wall.

The concrete and pump trucks were situated up by the road with the arm of the pump truck reaching over the basement wall.

Here's the pump truck - you can really see how uneven and sloped our future driveway is right now!

Here’s the pump truck – you can really see how uneven and sloped our future driveway is right now!

The arm on the pump truck was so big!

The arm on the pump truck was so big!

The crew worked so quickly and so well together - each of them had different jobs and it was really neat to watch how orchestrated the pour was.  You can tell they had all been working together for a while and really knew what they were doing.  They were making it look easy - but it was definitely hard work.

The crew worked so quickly and so well together – each of them had different jobs and it was really neat to watch how orchestrated the pour was. You can tell they had all been working together for a while and really knew what they were doing. They were making it look easy – but it was definitely hard work.

My dad came out and watched the slab pour too - it was fun having him there.

My dad came out and watched the slab pour too – it was fun having him there.

The final product!   Very exciting to have it done!!!

The final product! Very exciting to have it done!!!

Quick Design Changes

At the last minute, just before the plumbing went in, I shifted the wall between the guest shower and the tech closet to increase the size of the guest shower.  Hopefully it feels roomier in there (and there’s less splashing outside of the shower since I don’t want a shower door.  Other than that, Matt shifted a wall in the boys’ bathroom because the exterior foundation wall was longer than our architect had planned, and that created a thicker exterior wall.  Instead of shrinking the boys’ shower size (which wasn’t very big to begin with), he reduced the walking space by the sinks from 3’6” to 3’0”.

Week 7: Waterproofing, Plumbing, Well Pumping & Cabinetry Shopping

It seemed like a busy week this week – we started off the week with waterproofing the exterior of the basement walls; Matt is having them use a two-part system.  The first part is a spray-on bituminous surface sealant which is sprayed directly onto the concrete walls at a thickness of 40 mil.  The second part is a dimpled drainage sheet which get secured on the outside of the spray-on sealant.  This drainage sheet acts reduces the hydrostatic pressure against the wall – therefore keeping any water in the soil away from the basement wall by giving it a direct path to flow from the finished grade to the footing drains.  In addition, geotextile fabric is secured to the drainage sheet so that water can pass through, but it keeps soils out.  The type of drainage mat they’re installing is American Wick Drain’s Site Drain Sheet 180.  This was created for commercial usage and has higher standards and compression strength as compared to it’s counterpart product for the residential use.  I guess they actually started the waterproofing on Saturday, because they were wrapped up by Tuesday this week.

Here they are adding more gravel for the base material (and for drainage underneath the basement slab).

Here they are adding more gravel for the base material (and for drainage underneath the basement slab).

The first layer of the waterproofing, a bituminous spray-on, has been applied.

The first layer of the waterproofing, a bituminous spray-on, has been applied.

This is the 2nd layer of the waterproofing, a dimpled membrane with geotextile - American Wick Sheetdrain 180

This is the 2nd layer of the waterproofing, a dimpled membrane with geotextile – American Wick Drain Sheet 180

Both our boys came with us on Wednesday to see the progress.  Here they said

Both our boys came with us on Wednesday to see the progress. Here they said, “hey mom, look at us – on top of ROCK MOUNTAIN”!!

Here's Spencer standing next to the house - he was all about getting filthy dirty today.  At one point he even kicked his sandals off.  Ick - those went back on - immediately!

Here’s Spencer standing next to the house – he was all about getting filthy dirty today. At one point he even kicked his sandals off. Ick – those went back on – immediately!

Spencer found his special 'gem' rock.  He said he put it in a safe place to find it later (in the dirt).  Good luck Spencer! ;)

Spencer found his special ‘gem’ rock. He said he put it in a safe place to find it later (in the dirt). Good luck Spencer! 😉

On Wednesday the well pump guy came to install the pump in our well.  He installed an 8 gallon per minute pump, as not to over pump the well, and almost instantly had crystal clear water!  I haven’t seen it running yet, but Matt said it was pretty fantastic.  Typically it takes a few hours to get as clean of water as what they were getting right off the bat.  They let the pump run for nearly an hour and the recovery rate was good on the well too – it only took a couple of minutes (maybe 3?) to get the water level back up to where it was originally.  All in all, it’s super cool that the pump is doing fantastic!  The pump guy also chlorinated the water, so after a few days (probably on Monday) we’ll be able to take a sample and send it to the lab for testing of any natural-born contaminates in the water.

The pump's been installed ...on a tree??

The pump’s been installed …on a tree??

Thursday the plumber came to install all of the piping in the basement.  Joel and I had to double-check all of the locations of the fixtures in the basement and send Matt any plan changes along with dimensions to the fixtures.  Once the plumber installs them, and the basement slab is poured – that’s where they’re staying!  Joel took the week off of work so on Thursday he was out there seeing how the build was going.  The plumber had just showed up and apparently the laborer was pretty cranky that he had to dig out the gravel base to install the plumbing pipe.  I actually would be too – still not sure I understand why the gravel was placed before the plumbing was finished…but whatever.  Joel also saw them starting to backfill the house and regrade the site.

Some of the plumbing in the basement has been started - this is a picture of the guest bath.

Some of the plumbing in the basement has been started – this is a picture of the guest bath.

New equipment showed up at the house to regrade and backfill around the house.

New equipment showed up at the house to regrade and backfill around the house.

In action - regrading the back patio area...and the plumber looking annoyed about the digging!

In action – regrading the back patio area…and the plumber looks in disbelief about all of the digging ahead of him.

The giant stockpiles of dirt were removed from our future front lawn - you can actually see the basement walls peeking out if you're looking from the road now!

The giant stockpiles of dirt were removed from our future front lawn – you can actually see the basement walls peeking out if you’re looking from the road now!

By the end of the week, here's what the progress looked like in panorama.

By the end of the week, here’s what the progress looked like in panorama.

Cabinets

Besides all of the construction going on, on Monday my mom and I went up to Canyon Creek Cabinetry in Monroe to look at the different cabinet styles and construction types.  It was quite a haul to go up there, but definitely worth it once you’re there.  They have an amazing show room there – with example kitchen styles ranging from craftsman, to tuscan, to modern.  Of course, I shied away from most of those, and went for the simple shaker cabinet.  The only thing different than most shaker cabinets is that I’m really liking the beaded inset cabinets.  If it’s within the budget, we’ll definitely get those.  The cabinet boxes and drawers seem like they’re made very well too – all dovetailed and you have the option for plywood boxes & drawers.  There’s a couple of standard options that I love too – the drawers are automatically soft close, and since I want painted cabinets, they can do any color paint I can come up with.  All I need to do is bring them a color swatch and they can match it.  No extra charge!  How fantastic is that?

Tons of door options to choose from at Canyon Creek Cabinetry.

Tons of door options to choose from at Canyon Creek Cabinetry.

Here's what I ultimately settled on - painted shaker style with a beaded inset.  I had a feeling this is what I was going to choose before I even went in there.  But seeing it in person just solidified it for me!

Here’s what I ultimately settled on – painted shaker style with a beaded inset. I had a feeling this is what I was going to choose before I even went in there. But seeing it in person just solidified it for me!

Here's a pretty kitchen in their show room with full overlay shaker cabinets.

Here’s a pretty kitchen in their show room with full overlay shaker cabinets.

Gray cabinets - gorgeous!  And they can color match their cabinets to any color you choose!  Awesome!!  I just might end up doing a gray for the boys' bathroom...we'll see!

Gray cabinets – gorgeous! And they can color match their cabinets to any color you choose! Awesome!! I just might end up doing a gray for the boys’ bathroom…we’ll see!

Design Update

This week we also had to think about the HVAC area in the storage room off of the boys’ play room. The storage room was designed to have the basement laundry area when you first walk in, the HVAC storage closet to the left in the little ‘alcove’ and then behind the laundry we’d have room for the boys to store all of their toys (as shown in the pic below). I swear that toy storage was my worst enemy in our old house – toys were everywhere and I was constantly trying to come up with organization solutions for all of them. It doesn’t help that the boys are 3 ½ years apart, so their toys ranged from baby toys to legos. Now it’s a bit better since Spencer is getting older, but there’s definitely a ‘mine vs. his’ attitude with their favorites – growing up with a sibling, totally understandable. The other issue is that toys are HUGE! Both boys love playing with the Imaginext toys and they’re SO BIG. In the old house, they filled up a huge armoire and that was with stacking and cramming them in. I even had to give some away so that we could house them all. Needless to say, the toy storage is a MUST for this home. Here’s a look at our original design for the space:

Original Toy Storage & HVAC room layout.

Original Toy Storage & HVAC room layout.

The problem is that we’ve now come to realize that the HVAC ‘alcove’ is too small. The size was roughly 6’ x 4.5’ and to hold two different HVAC systems (one for upstairs and one for downstairs), as well as hot water tanks (haven’t decided…might have two of those as well), it simply just won’t fit in the space. Redesign!!! And it needs to be thought through before the plumber comes in a few days to install the water lines and drains (like for the washing machine) which will be poured under the slab. The solution we came up with is shown below. We decided to move the laundry to the ‘alcove’ area, toy storage where the laundry was, and now the entire back of the storage room (6’ x 14’) is now the HVAC area – plenty big enough. I kept this walled off and with a door to not only add wall to line shelves for the toys, but also to keep the toys out of that space. That’s all I’d need is Nerf darts ending up in my furnaces…or heat pumps (still haven’t decided on that either). That’ll be a decision for a different time. 🙂

Here's the new design of the toy storage & HVAC space.  More space has been given to the HVAC equipment.

Here’s the new design of the toy storage & HVAC space. More space has been given to the HVAC equipment.

You know, it’s totally nice knowing CAD and being able to make all of these changes myself. I could see how working a lot with an architect through construction could really add up to some serious money for all the changes on the fly. I just make the change, get the dimensions and give it to Matt. Since we’re catching these things before it’s getting constructed, it’s been perfect!

Week 6: Walls and Water

On Monday this week they were out there pouring the basement walls – about 75 cubic yards of concrete! The foundation guys said that this is probably the biggest concrete job that they’ve done. How crazy is that? I think it’s probably because most homes in the northwest don’t have basements – and that’s really where you utilize a lot of concrete in homes. Otherwise, it’s typically just for the footings – no walls. Besides the walls, they also poured a couple of the footings for the deck. I wasn’t expecting that at all! My dad and his friend Steve met me out there on Monday at lunch to see the concrete being poured – it was looking like a ‘real’ jobsite out there…everyone bustling about!  By Wednesday the forms were stripped and just like that, the guys were moving on to their next project!  Friday some of the gravel was delivered and loaded into the house using a conveyor belt system.  It totally reminds me of our I-405 project with moving all that excavated dirt.  Definitely saves time and energy to do it that way!

Here's the concrete pump truck.

Here’s the concrete pump truck.

I wish the boys were here to see this - this guy has a remote control to maneuver the articulating robotic arm of the pump truck.

I wish the boys were here to see this – this guy has a remote control to maneuver the articulating robotic arm of the pump truck.

These guys have the scary work - standing on top of 10' walls, filling them with concrete and then vibrating them.  My dream job?  No thank you!

These guys have the scary work – standing on top of 10′ walls, filling them with concrete and then vibrating them. My dream job? No thank you!

The formwork has all been stripped and now you can really see the concrete walls & footings in the basement.

The formwork has all been stripped and now you can really see the concrete walls & footings in the basement.

Another view of the basement walls - this time from standing in the (future) back yard.

Another view of the basement walls – this time from standing in the (future) back yard.

By Friday they started to fill the footings with gravel using a conveyor belt system.  Reminds me of working on I-405!

By Friday they started to fill the footings with gravel using a conveyor belt system. Reminds me of working on I-405!

Well Update

Joel and I left for vacation to North Carolina to visit our friends Andy & Jackie on Wednesday morning, but by Wednesday afternoon we had received a call from Matt saying that our well guys had hit water! At 10 gallons per minute and 350 feet deep, we were ecstatic! YAY!!!  Next week we’ll have the pump guy out to check out the recovery rate and clarity.

There it is - our well!  At 10 gallons per minute and 350' deep, we're done!

There it is – our well! At 10 gallons per minute and 350′ deep, we’re done!

Design Update

This week Matt also let us know that we’ll need to start thinking more about the layout of the bar area. The plumbers are coming to install everything that will need to be in the basement slab next week, so we needed to get the configuration nailed down. The last thing we’d want is drain pipes for the sink & dishwasher in locations that weren’t ideal. Joel and I spent some time on the weekend before our trip to really measure out the bar area and make some design decisions. We looked into some appliances and their dimensions and have come up with a new bar layout.

Here's the new bar layout that we've come up with for the basement.  There might be a few things to work out after we talk to the cabinetry designers - but at least it's a good starting point!

Here’s the new bar layout that we’ve come up with for the basement. There might be a few things to work out after we talk to the cabinetry designers – but at least it’s a good starting point!

The bar area and all of the audio/video in the house are really the only thing Joel really has strong opinions on. I told him early-on those were ‘his areas’ of the house to deal with because I really don’t care as much as him. And for the rest of the house – he just goes along with most of what I want (as long as it’s within budget)! Matt has done a really good job at reminding me of our budget too, so I can’t wander too far!

Week 5: Forming Basement Walls

This week Matt’s crew continued to work on our foundation.  They started the week with only a bit of formwork and rebar up and by the end of the week our entire basement walls are formed and ready to be poured early next week.

Monday evening we went out to see the progress from the day and we were pretty excited to see the formwork for the cast-in-place basement walls up.  Cameron’s my little adventurous construction guy – he always wants to hop out of the car with me and go check things out.  Here’s a pic and you can see that Spencer isn’t around (he’s hanging out in the SUV watching a show on Joel’s phone), and even Joel’s standing off to the side.  It’s probably for the best anyhow that Spencer isn’t bumming around the site right now – there’s tons of stuff he could get hurt on – nails, rebar, concrete, formwork, etc.  Every time I ask him if he wants to check it out he says, “Is the house all built?  No?  Ok, I’ll just stay in the car.”

Cameron always wants to check the progress out with me!  Love it!

Cameron always wants to check the progress out with me! Love it!

Not Cameron though – he always wants to walk around the site and see up close what’s going on.  I love it!  And he’s always asking questions so it’s fun to explain things to him.  Bring back your 2nd grade science fair days, because on Monday evening Cameron wanted to do an experiment.  Hypothesis: when you throw them, which object (a rock or a stick) will make the biggest hole in the mud coming from the well digging?  Cameron’s conclusion: the rock makes a deeper hole and a taller “splash”, but the stick makes a shallower but wider hole.  🙂  Such a cute kiddo!

Cameron's experiment today - rock versus stick in the mud.

Cameron’s experiment today – rock versus stick in the mud.

Here’s some other pictures from throughout the week…

Rebar at sunset - whata view!

Rebar at sunset – whata view!

A quick pic inside the walls at Spencer's room.

A quick pic inside the walls at Spencer’s room.

At work it's standard to have

At work it’s standard to have “safety moments” before each meeting…had to share this one.

Here's the garage - it seems like such a waste that it's all going to be filled in with dirt - we're not having any living space beneath the garage.  Cameron wanted to make it an indoor basketball court!  There's an idea!

Here’s the garage – it seems like such a waste that it’s all going to be filled in with dirt since we’re not having any living space beneath the garage. Cameron wanted to make it an indoor basketball court…there’s an idea!

By the end of the day on Friday it's all formed and ready for the pour on Monday!

By the end of the day on Friday it’s all formed and ready for the pour on Monday!

Drilling Update

The drilling is moving along too…they started the week at 210’ deep just having passed through some major rock last week and on Monday moved on to drilling through clay.  By the end of the week, they were at 340′ and still in clay.  Judging on the other wells on our street, I think they should hit water this week.  Cross our fingers!

Design Update

This week we had a quick decision that we needed to make. Matt called to talk about the windows on the side of the garage. He needed a place to put the electrical & gas meter, and plan a place for our hose bib. The logical place would be to put them on the side of the garage, but we have windows there. The only place the electrical meter could fit would be in-between the first two windows. I guess this could have been ok, but I think that it really would have looked weird to have had the meter stuck dead center in the middle of the windows – like it was some sort of feature. Probably the easiest decision would have been to just nix the windows on the side of the garage. But since that side of the garage is angled to face the road, I really liked the idea of having windows to add curb appeal. So we decided to push the windows together to create room for the electrical meter to the right of the pair of windows. It’s the same layout as what’s set up further down on the garage wall, so it looks good – and gives Matt enough space to work and place the utilities. It’s a small change, but I believe that thinking through even the smallest of details will makes a home look so much better.

Week 4: Footings & Pour

This week they were constructing the footings for our house.  The started the week with only our surveyed corners, and by Tuesday all of the formwork and rebar was constructed!  Wednesday they poured the footings, which was super exciting to see, and by Friday they had already started on forming the walls.

Monday they made all the cuts and had it laid out.

Monday they made all the cuts and had it laid out.

Just some quick math for the garage retaining wall's footing...they must have run out of graph paper ;)

Just some quick math for the garage retaining wall’s footing…they must have run out of graph paper 😉

Joel and I took the boys to the property on Tuesday and Cameron was shocked at how small his room seemed.  Overall the house feels big, but when you’re looking at one bedroom it’s strange but it does feel small.  I think it’s because you’re out there with nothing else around you except acres of trees (and stockpiles of dirt).  So when you compare it to your surroundings, a 13’x15′ space does seem little.  I guaranteed him that it would be plenty big – and that it’s bigger than the room he’s in now which he’s even sharing with Spencer!

Here's a shot of Joel and the boys standing next to the excavation for the basement - just to give you some scale.

Here’s a shot of Joel and the boys standing next to the excavation for the basement – just to give you some scale.

By the end of the day on Tuesday the formwork was up and pretty close to being ready for concrete.

By the end of the day on Tuesday the formwork was up and pretty close to being ready for concrete.

On Wednesday they poured the footings.  From the concrete truck to the pump to our footings.

On Wednesday they poured the footings. From the concrete truck to the pump to our footings.

They reached over the excavated area to get to our footings.

They reached over the excavated area to get to our footings.

Another picture of the pump and our footings.

Another picture of them pumping the concrete for our footings.

Here's the finished product Wednesday night...we have footings!

Here’s the finished product Wednesday night…we have footings!

Check out that rebar :)

Check out that rebar 🙂

There's Cameron on Thursday - standing in his bedroom.

There’s Cameron standing in his bedroom on Thursday.

The guys even worked the Friday before the 4th of July!  Lucky for us!  And they started to form the walls up in the basement.

The guys even worked the Friday before the 4th of July! Lucky for us! And they started to form the walls up in the basement.

We did have to make one design decision this week – the ceiling height in the basement.  We designed the upstairs of the home to have a standard height of 10’ – most rooms are 10’, some are 9’, one is 11’.  The basement to have a consistent height of 10’.  However, to form the 10’ basement walls, they would have needed to use an extra row of formwork.  To save a couple thousand dollars we opted to reduce the height downstairs by about 4”.  Everyone’s guaranteed me that we won’t be able to notice a few inches off the ceiling when we’re already over 9’6”.  Let’s hope not!  In any case, maybe we’ll be able to use that extra money to upgrade something that we’ll actually notice and use.

Drilling Update

They’re still drilling for water this week.  Last week they hit a pretty big rock and the guy ended up having to drive to Eugene on Monday to pick up a new part for the drill.  And by Wednesday they had broken another part and still not completely gotten through the rock!  I told Matt to have them dig it up so we can use it for landscaping…if only it weren’t ~200-feet deep 🙂 Wednesday evening they parts of the drill home to fix them and by mid-morning on Thursday they had FINALLY gotten through the rock and were back to drilling.  So not much progress has been made in depth (only at 210-feet) on the well this week, but they did make it through the rock, so that’s good news.  Let’s hope they find water next week!

Week 3: Drilling Deeper

This week has been pretty uneventful as far as our house building is concerned.  They were supposed to have started forming the footings this week, but the only thing that has been done is some formwork and some rebar have been dropped off at the property.  Let’s hope they start Monday!

Beyond that, they keep drilling for the well.  Early in the week they found an aquifer of water at about 60 feet deep, with a rate of only 6 gallons per minute.  Being that shallow and with only gravel/sand above it, it’s considered an “unconfined aquifer” and not ideal for a well used for potable water.  In addition to that, with such a low flow, we told them to keep going.  Towards the end of the week, Matt told us that at 170’ deep they hit rock, so they needed to put on a new drill head. They’re now at 190’ down, they’re drilling through gray clay.  Hopefully once they are through the impervious clay layer they’ll find another aquifer for us.  The gray clay is fantastic because it’s impermeable and any bacteria that could come from the surface (like doggie-do) can’t pass through that layer. Thus, (when) they do find an aquifer, the gray clay protects it – ta-da… a “confined aquifer” perfect for drinking (after treatment of course)!

A confined aquifer protected by an impermeable clay layer - hoping to find water in a few days here!

A confined aquifer protected by an impermeable clay layer – hoping to find water in a few days here!

In King County, the Department of Ecology records all wells and actually has them mapped and available to the public for review on their website.  It’s a pretty easy map search to find all of the wells in your area.  In doing so, you can check out how deep you’d expect your well to be (and get an idea of the type of soils near your property).  Based on other well logs in the neighborhood (see below), I would expect to be around 350’ deep (or around there) to find our water.  Let’s hope it’s less, but only time will tell!

Other private wells on our street show that we should hope to find water between 300' and 400' deep.

Four other private wells on our street show that we should hope to find water between 300′ and 400′ deep.

Week 2: Our Private Well Drilling

Our property is on a street that doesn’t have a water main from the local utility/water district.  So, that means that everyone has their own private well on their properties.  And since ours hasn’t been installed, that was one of the first orders of work (once preliminary grading was complete).

Johnson Drilling, the well driller arrived at the property on Wednesday and began to drill the well.  They can drill down about 60 feet per day (unless they hit rocks, then the rate/hour is reduced).  At a rate of $40 per foot, I’d like them to spend as little time at our place as they can!  Ultimately, they need to hit an aquifer with a good rate of water flow (gallons per minute) in order to pump enough water for our house.  We want to be above 10 gpm, and ideally more like 20 gpm.

Since the other homes in the neighborhood all have wells too, we’re able to review the well logs for their wells and see how deep those wells are.  Unfortunately they’re all over the map, ranging from 100’ deep to 450’ deep…so we have no idea where ours will end up.  At the end of the day Friday they still were drilling.  And apparently they must have hit some rocks because they’re only 60′ deep now.  Eeekkk.  One good thing is that at 60′ they did hit water, but only at a rate of 6 gpm.  We’ll see next week where they end up!  Drilling will pick back up on Tuesday.

Johnson Drilling arrived on site Wednesday to mobilize for the well drilling.

Johnson Drilling arrived on site Wednesday to mobilize for the well drilling.

Check out the buckets they had..."Let's Do This."  Love that!

Check out the buckets they had…”Let’s Do This.” Love that!

Our well site is located at the tree line in the far northeast corner of the property.

Our well site is located at the tree line in the far northeast corner of the cleared area of our property.

Two trucks were there, one for drilling and the other for hauling the steel casing for the drill.  Vintage trucks though - I think my Uncle Greg needs to sell them some new Mack's!

Two trucks were there, one for drilling and the other for hauling the steel casing for the drill. I can’t believe they showed up with Kenworth’s…apparently they don’t know their clients very well 😉 With those vintage trucks, I think it’s time they invested in a couple new Mack’s!

Here's the drill in action, which is located on the back end of the tan truck.

Here’s the drill in action, which is located on the back end of the tan truck.

The turquoise truck hauled all of the casing pipe.

The turquoise truck hauled all of the casing pipe.

Check out how close they are.  Those are some tight spaces they're working in!

Those are some tight spaces they’re working in!

Week 1: Surveying

On Saturday, Fred (a surveyor from my work) and I located 20 of the house corners so that they could get started on building the foundation footings next week.  After nearly 7 ½ hours outside in the sun we were done!  It was gorgeous outside and actually a lot of fun.  I haven’t worked with Fred all that much since he’s usually in the field and I’m in the office, but it was really great to get to know him more and he re-taught me a lot about surveying.  Things have really changed since my surveying class at UW 12 years ago…the instruments that we used today were robotic and would automatically follow and track wherever you moved the prism.  And of course we did things perfectly – to the nearest hundredth.  If Matt’s crew builds it that accurately it’d be amazing!

To save a bit of money, instead of using a surveyor to stake out the house for the excavation, Matt used known locations on the property and with a few measurements I gave him to each of the property corners he got a rough idea of where the house was going to sit.  But he had to tape them off and on a sloped site that can be a little tricky!  To give the crew some working room, over-excavate by about 5′ anyhow for the foundation so it didn’t need to be exact.  And although it would have been nice to have a surveyor prior to excavating (so you knew that you were absolutely sure you were digging in the right spot), not doing so saved us hundreds!  Fred was really impressed at how accurate Matt measured out the excavation dig though – he was pretty well on point with being 5′ wider than the actual house corners and extremely parallel too!  In addition to surveying the house corners, we also surveyed the proposed well location which is pretty important since the 100’ well radius covenant area encroaches onto our neighbor’s property.

A panoramic shot of the property at the beginning of the day.

A panoramic shot of the property at the beginning of the day.

Our survey truck

Our survey truck.

The total station and prism that we used to survey the house corners.

The total station and prism that we used to survey the house corners.

The total station we used which was so much more high-tech than then ones I learned surveying on at UW!

The total station we used which was so much more high-tech than then ones I learned surveying on at UW!

Quick shot of one of the property corners we set.

Quick shot of one of the property corners we set.

At the end of the day we had all 20 points surveyed for the house.

At the end of the day we had all 20 points surveyed for the house.

Here is our site plan which ahead of time I located all of the coordinates for the house corner points (and the well location) to guide us throughout the day.

Here is our site plan.  Earlier in the week, I located all of the coordinates for the house corner points (and the well location) to guide us throughout the day.

Just as we were surveying the well location, Brad Johnson from Johnson Drilling (well driller) came by to check out the graded road.  As it turns out, Matt needs to increase the area of the drilling pad some more next week since the well wasn’t quite in the location we had thought it was.  Good thing we surveyed it!

After we were done surveying, Joel brought the boys by to check it out.  Of course now that it was staked it was fun for them to see where their bedrooms were exactly going to be!

Check out each of the boys standing in their future bedrooms!

Check out each of the boys standing in their future bedrooms!

Spencer on top of the world...errr, stockpile!

Spencer on top of the world…errr, stockpile!

Week 1: Groundbreaking & Excavating

And so it begins!  Construction FINALLY started on the house!!!!  Monday June 8th was our official groundbreaking at the property and we’re beyond excited for Matt to get started.  The excavator was delivered last Friday and after a family BBQ at our house on Saturday we took the boys and my parents over to check it out!

The boys pose by the excavator - they were super excited to check it out on Saturday.

The boys pose by the excavator – they were super excited to check it out on Saturday.

And since then things have been changing daily at the property.  It is absolutely crazy the progress that happens in a week.  The beginning of the week started with clearing the brush that’s been growing since the last time the property was mowed, as well as taking down a few trees that needed to be removed.  I’m sure that chainsawing trees isn’t exactly the most enjoyable task to be doing in 80-degree heat, but the property looks so much better for it!

The week started with clearing brush and a few trees.

The week started with clearing brush and a few trees.

At the beginning of the week our property was green...everywhere!

At the beginning of the week our property was green…everywhere!

This is what it looked like after a bit of progress on Monday.

This is what it looked like Monday evening after a day of progress.

Excavating for the foundation has by far been the biggest event of the week though.  It’s wild how much has changed.  At the beginning of the week our property looked like an overgrown mess and now property has been excavated for the basement and foundation and there’s dirt stockpiles everywhere. There was already a huge pile of dirt by Tuesday evening and the boys LOVED climbing all over it!

The excavator!

The excavator!

The boys on top of the stockpile in our future backyard.

The boys on top of the stockpile in our future backyard.

Cameron & Spencer rocking on :)

Cameron & Spencer rocking on 🙂

We let the boys sit on the bulldozer – Cameron thought it was so cool!

Spencer thought the excavator was awesome.  I think he emptied about 2 cups of dirt out of his shoes on it!

Spencer thought the excavator was awesome. I think he emptied about 2 cups of dirt out of his shoes on it!

By Wednesday there was already two stockpiles up by the street as well as another lower on the property.

By Wednesday there was already two stockpiles up by the street as well as another lower on the property.

Cameron standing on top of one stockpile, checking out the excavator and the amount of work already done!

Cameron standing on top of a stockpile, checking out the excavator and the amount of work already done!

A quick panoramic of the property on Tuesday evening.

A quick panoramic of the property on Tuesday evening.

On Friday, Cameron stayed home from school because he was sick and so I took him over to the property for a couple field trips today J  He had so much fun as we got to watch the excavator and bulldozer in action!

Cameron sat on top of the stockpile for at least 20 minutes watching the action.

Cameron sat on top of the stockpile for at least 20 minutes watching the action.  He had a blast!

Checking out the bulldozer.

Checking out the bulldozer.

The excavator at work.  Way better to watch it in action!

The excavator at work. Way better to watch it in action!

In addition to all the grading, Tanner Electric arrived on site to install our underground power line and transformer.  I was hoping the power line install would only take a day, but it actually spilled over into Wednesday too.  The location of the transformer on the property looks great though – it’s on the far side of the house and we set it back about 15’ off the road so that we can ‘hid’ it in the future with some shrubs.

Tanner electric digging the trench for the underground power line.

Tanner electric digging the trench for the underground power line.

After the first day of their work, they were nearly complete with the powerline.

After the first day of their work, they were nearly complete with the powerline.

Tanner Electric's truck!

Tanner Electric’s truck!

Our transformer tucked back off the street.

Our transformer tucked back off the street (along with the temp power pole for construction).