Week 22: HVAC, Electrical & Windows

The HVAC was worked on for the house this week which included setting up the furnaces which will back up the heat pump.  The furnace for the downstairs was placed in the HVAC room downstairs by the boys’ playroom, and it was most efficient to put the furnace for the main level in the attic of the garage.  Besides installing both of those, it looks like the vents have all been placed and all 4 of the cold air returns were also installed (two on each level of the home).

It was most efficient to put the upstairs furnace in the attic.

It was most efficient to put the upstairs furnace in the attic.

The downstairs furnace is located in the HVAC room.

The downstairs furnace is located in the HVAC room.

Electrical work began this week and was laid out based on our walk thru last week.  On Sunday, Joel and I went to check things out…and confirm light switch locations.  A few of them were in the wrong spots, but for the most part things were in the correct locations.

The electrical sub (Modern Wiring) started on the house this week.

The electrical sub (Modern Wiring) started on the house this week.

And even more fun (and with a bigger impact) was that the majority of the windows were delivered and quite a bit of them were installed!  I think they look great, and love the grid layout we chose.  I can’t wait to see all of them installed.  It’ll end up being a couple weeks for all of them to get here.  The windows with the arched tops all have a bit longer lead time than the rectangular ones.

Some of the windows were installed in the front of the house this week.

Some of the windows were installed in the front of the house this week.

Although we're still missing the french doors and the oval windows, the back wall of the great room is starting to take shape.

Although we’re still missing the french doors and the oval windows, the back wall of the great room is starting to take shape.

I love how the windows turned out in the staircase.

I love how the windows turned out in the staircase.

The windows in the informal dining area in the kitchen look amazing! It's too bad that the construction film makes it so we can't see outside anymore. At least that'll protect the glass until construction is finished though.

The windows in the informal dining area in the kitchen look amazing! It’s too bad that the construction film makes it so we can’t see outside anymore. At least that’ll protect the glass until construction is finished though.

Here's what the windows look like from the outside of the house. These ones are above the kitchen sink area.

Here’s what the windows look like from the outside of the house. These ones are above the kitchen sink area.

Besides all of the things happening at the house, my mom and I also went to Canyon Creek Cabinetry on Thursday to figure out all of the cabinets for the house.  We did our initial walk thru a couple of weeks ago.  After that, they drafted up the initial design for the cabinets…but of course I had markups and things that I wanted changed.  So we met up with Andy at Canyon Creek to discuss all of the changes.  He’s going to revise the drawings (and the cost estimate) – hopefully we’ll get those this next week.  Then they’ll be finalized!